Work continues on the deck edge toe rails. One is complete and the second one is going into the jig for some final-finish work.

1 deck edges

We received a large shipment of nickel plating from R.E. Sturdy, our third such shipment from them. Again, we give them our most sincere thanks and praise for donating to our team’s success.

2 received new ni plating

Also received in that shipment were plated topmast shroud turnbuckles and mast hoops; thank you Tom and Dorothy!

3. And mast hoops and topmast shroud turnbuckles

Keith continues to make amazing progress on the spreader and now it is on to the truss!

4. Spreader progresses

Finally, we moved our benches to align the mast, topmast, and topsail yard so initial work on rigging can be done. This will also enable us to complete our topmast with sheaves and cone parts.

5. Alignment

1 thought on “Deck Edge Update, Shipments, and Spreader Progress

  1. Maurice Robson

    I visited your workshop in June and was very impressed by the progress made and great work you are doing! Watching y our blog with keen interest! Maurice

    Reply

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s